IIBA Certification of Capability in Business Analysis (CCBA) CCBA Question # 17 Topic 2 Discussion

IIBA Certification of Capability in Business Analysis (CCBA) CCBA Question # 17 Topic 2 Discussion

CCBA Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

A business analyst (BA) is working on a project that follows incremental and iterative approaches. The BA and the stakeholders have shortlisted several user stories to be considered in the project scope. Which of the following methods would enable them to arrive at a common understanding on delivering value in the product and ranking the stories?


A.

Story decomposition


B.

State modelling


C.

Value stream mapping


D.

MoSCoW prioritization