IIBA Certification of Capability in Business Analysis (CCBA) CCBA Question # 168 Topic 17 Discussion
CCBA Exam Topic 17 Question 168 Discussion:
Question #: 168
Topic #: 17
Stakeholders must be able to determine the audit and approval history of requirements and designs. Which of the following provides a means to document traceability and change?
Comprehensive and Detailed Explanation:Requirements management toolsprovidea structured way to document requirement changes, maintain traceability, and track approvals.
BABOK® Guide (Chapter 5.1 - Trace Requirements)states thattraceability ensures every requirement is linked to its origin and tracks changes throughout the project lifecycle.
Risk analysis and management (Option A)addresses uncertainties but does not document requirement history.
Acceptance and evaluation criteria (Option B)define success conditions but do not track approvals.
Legal and regulatory information (Option D)ensures compliance but does not track requirement history.