IIBA Certified Business Analysis Professional CBAP Question # 69 Topic 7 Discussion
CBAP Exam Topic 7 Question 69 Discussion:
Question #: 69
Topic #: 7
You are the business analyst for your organization. Management has asked that you create a stakeholder map as part of the conduct stakeholder analysis process.
What is a stakeholder map?
A.
A stakeholder map is a visual diagram that shows the connection among positive and negative stakeholder
B.
A stakeholder map is a visual diagram that illustrates where the stakeholders are geographically located.
C.
A stakeholder map is a visual diagram that depicts the stakeholders' actions as responsible, accountable consult, and inform.
D.
A stakeholder map is a visual diagram that depicts the relationship of the stakeholders to the solution and to one another.
A stakeholder map is a strategic tool that helps to identify and analyze the stakeholders involved in a project or business initiative. It shows the level of interest, influence, power, and impact of each stakeholder, as well as their expectations, needs, and concerns. A stakeholder map also illustrates how the stakeholders are related to each other and to the solution, and how they may affect or be affected by the project outcomes. A stakeholder map can help to plan and manage stakeholder engagement, communication, and collaboration throughout the project lifecycle1234. References: 1: Stakeholder Analysis and Mapping: Getting Started Smartsheet1 2: What Is A Stakeholder Analysis? Everything You Need To Know2 3: Mastering Stakeholder Mapping: An Essential Guide for Stakeholder …4 4: Stakeholder Mapping | What is Stakeholder Mapping + Examples - Boréalis5