New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

IIBA Certified Business Analysis Professional CBAP Question # 50 Topic 6 Discussion

IIBA Certified Business Analysis Professional CBAP Question # 50 Topic 6 Discussion

CBAP Exam Topic 6 Question 50 Discussion:
Question #: 50
Topic #: 6

Which of the following types of charts shows which resources are needed in the project and allows you to group the resources by project phase or other attributes?


A.

Pareto chart


B.

Organizational Breakdown Structure


C.

Gantt chart


D.

Resource Breakdown Structure


Get Premium CBAP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.