IIBA Certified Business Analysis Professional CBAP Question # 41 Topic 5 Discussion

IIBA Certified Business Analysis Professional CBAP Question # 41 Topic 5 Discussion

CBAP Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

Which of the following is a visual decomposition of the project scope?


A.

Budgeted Cost of Work Scheduled (BCWS)


B.

Resource Breakdown Structure (RBS)


C.

product breakdown structure (PBS)


D.

Work Breakdown Structure (WBS)


Get Premium CBAP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.