CBAP Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

Which of the following is a visual decomposition of the project scope?


A.

Budgeted Cost of Work Scheduled (BCWS)


B.

Resource Breakdown Structure (RBS)


C.

product breakdown structure (PBS)


D.

Work Breakdown Structure (WBS)