IIA Business Knowledge for Internal Auditing IIA-CIA-Part3 Question # 149 Topic 15 Discussion

IIA Business Knowledge for Internal Auditing IIA-CIA-Part3 Question # 149 Topic 15 Discussion

IIA-CIA-Part3 Exam Topic 15 Question 149 Discussion:
Question #: 149
Topic #: 15

The project manager responsible for overseeing a controversial project decides to accept the risks associated with the project launch. These risks might have a significant impact on the organization meeting its environmental sustainability goals. Which of the following is the most appropriate next step for the chief audit executive to take in response to the decision?


A.

Educate employees working on the project launch about the risks


B.

Notify the board about the significant risks the organization might face


C.

Communicate the risks to senior management


D.

Instruct the project manager to stop the controversial project development


Get Premium IIA-CIA-Part3 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.