IIA Practice of Internal Auditing IIA-CIA-Part2 Question # 52 Topic 6 Discussion

IIA Practice of Internal Auditing IIA-CIA-Part2 Question # 52 Topic 6 Discussion

IIA-CIA-Part2 Exam Topic 6 Question 52 Discussion:
Question #: 52
Topic #: 6

An internal auditor at a bank informed the branch manager of a malfunctioning lock on one of the vaults. The risk associated with this issue was deemed significant by the chief audit executive (CAE), and immediate remediation was recommended. However, during a follow-up engagement, the branch manager told the CAE that the risk was actually not significant, hence no action was taken. What is the most appropriate next step for the CAE?


A.

Inform senior management that the branch manager decided to cancel the committed action plan without any previous communication.


B.

Discuss the issue with the board, which has ultimate responsibility to resolve this risk.


C.

Have another discussion with the branch manager, attempt to change his view, and encourage him to implement the recommendations.


D.

Document the branch manager’s decision to accept the risk; otherwise, no other specific course of action is required.


Get Premium IIA-CIA-Part2 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.