New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

IFMA Certified Facility Manager CFM Question # 72 Topic 8 Discussion

IFMA Certified Facility Manager CFM Question # 72 Topic 8 Discussion

CFM Exam Topic 8 Question 72 Discussion:
Question #: 72
Topic #: 8

You are tasked with building four conference rooms with standard conference features. The project scope and schedule are clearly defined. To minimize risk to the organization, what type of contract should be used to procure the needed services?


A.

Cost-Plus-Fee Contract


B.

Cost-Reimbursable Contract


C.

Fixed-Price Contract


D.

Time and Material Contract


Get Premium CFM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.