New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

IFMA Certified Facility Manager CFM Question # 70 Topic 8 Discussion

IFMA Certified Facility Manager CFM Question # 70 Topic 8 Discussion

CFM Exam Topic 8 Question 70 Discussion:
Question #: 70
Topic #: 8

When is the final payment made for a large-scale construction project?


A.

At the time of substantial completion


B.

After no less than 100% of the construction work has been completed


C.

Upon receipt of all deliverables, closeout documents, and lien releases


Get Premium CFM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.