A punch-list (defects list) walk-through is conducted to identify construction issues that must be corrected before final payment (Option A).
Why Option A is Correct?
It ensures the contractor has completed all work per the contract specifications before the project is officially accepted.
It protects the facility owner from paying for incomplete or substandard work.
IFMA’s Project Management Core Competency states that final inspections and punch lists ensure compliance before closure.
Why Other Options Are Incorrect?
Option B (Ensuring site is free from debris): While cleanliness is important, a punch-list is for identifying construction defects, not cleanup.
Option C (Discovering what needs completion): A punch-list is not about discovering tasks but ensuring contractual obligations are met.
[Reference:, IFMA Core Competency: Project Management – Punch-list process in construction projects., Source: IFMA Construction Management Guide (IFMA, 2023)., , ]