An active job plan cannot be edited directly. The Revise Job Plan action creates a copy with the status PNDREV (pending revision), in which tasks and other details can be changed. When the revision is made active, the previous version becomes REVISED and the new version continues the job plan. The flow control actions only affect how task sequencing works, and Simulate Job Plan only tests the plan.