On the Scheduling Dashboard, what kind of information is displayed on the Resource Leveling tab?


A.

The total cost of the work scheduled during the time period


B.

A comparison of projected versus actual hours for planned work on a schedule


C.

Work order assignments by labor and crew


D.

Resource allocation and planned work by craft and crew type