Maximo stores data at four levels: System, Set, Organization and Site. Calendars, together with their shifts, are created in the Calendars application at the Organization level, so every site in that organization can use them. They drive work periods and non-working time for labor, crews, assets, locations, preventive maintenance and SLAs, as well as scheduling. A calendar is not shared between organizations and is not specific to one site.