Exact Extract — ECE Operation Process Overview:
“Preparations for the container service (software package interconnection and configuration operated by O & M administrators, others operated by operation administrators).”
Technical Explanation:
Options B and D are correct because they represent container service preparation activities assigned to the operations management workflow rather than infrastructure interconnection or Kubernetes cluster creation.
Huawei DCS provides Elastic Container Engine (ECE) capabilities for deploying and managing Kubernetes-based container environments. Preparing these services requires coordination between infrastructure O & M administrators and operation administrators.
Option A is incorrect. Interconnecting with NCE-Fabric resources is explicitly assigned to O & M administrators. This includes configuring cloud platform interconnection information and establishing the relevant SDN management connectivity.
Option B is correct. Configuring NIC routes for container nodes is included in the container service preparation workflow and falls under the operation administrator activities identified in the course.
Option C is incorrect. Creating a Kubernetes cluster belongs to the subsequent cluster management phase. It is performed through the eDME operation portal using the appropriate VDC administrator or operator permissions rather than being classified as an initial preparation task.
Option D is correct. Creating the required VDC account establishes the administrative and tenant resource context needed before container service provisioning.
Correctly separating these activities ensures that infrastructure networking is prepared before tenant-level container resources are created.
[Reference: HCSP-O&M-DCS Training Material — DCS Features in the Lightweight Cloud Scenario, ECE Operation Process Overview, PDF pages 287–288, slide 115. Lab Guide — Section 1.1, SDN Deployment Requirements.]