H19-260_V2.0 Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

Which of the following micro-grid scenarios requires a backup time of more than 6 hours?


A.

Industrial and commercial load micro-network


B.

New city micro-grid


C.

Civil load-like micro-grid


D.

Industrial load micro-grid