Which of the following statements about the Huawei prefabricated modular data center solution are incorrect?


A.

Property certificates cannot be obtained for prefabricated modular data centers. Therefore, assets must be depreciated by equipment.


B.

The FusionDC1000C uses the in-row air cooling solution.


C.

For a data center with 1000 cabinets, the TTM of the prefabricated modular construction mode is six months, excluding the time for planning and construction application and design.


D.

By default, the power supply module of the FusionDC1000C outside China includes a transformer.