HPE Network Data Center Professional Architect Exam HPE7-A12 Question # 18 Topic 2 Discussion

HPE Network Data Center Professional Architect Exam HPE7-A12 Question # 18 Topic 2 Discussion

HPE7-A12 Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

The customer runs a 24/7 production facility and is concerned that the migration could interrupt the production line.

Which two approaches can minimize or eliminate this disruption? Choose two.


A.

Whenever possible, ramp up the new infrastructure in parallel and do transparent switching from old to new core switch.


B.

Replace one access switch at a time and patch the ports by using a patch plan.


C.

Create a Migration Plan which describes a phased approach, i.e. access layer first, distribution layer second, etc.


D.

Close the production site for at least 1 day to do a big-bang approach