Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

HIMSS Certified Professional in Healthcare Information and Management Systems CPHIMS Question # 22 Topic 3 Discussion

HIMSS Certified Professional in Healthcare Information and Management Systems CPHIMS Question # 22 Topic 3 Discussion

CPHIMS Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

During the requirements phase of an implementation project, the consulting team discovers a gap that is critical to the success of the project; however, it involves additional cost and resources. What step would be performed by the project manager to address this?


A.

Include activities in the change management plan to ensure the gap is communicated and understood by staff and resources on the program.


B.

Update the cost and timeline of activities and notify the downstream impact to the stakeholders.


C.

Create a change request and ensure review and approval from the key stakeholders and sponsors.


D.

Conduct stakeholder interviews to understand the challenges due to the gap identified.


Get Premium CPHIMS Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.