Question #: 105
Topic #: 11

You work as a project manager for PassGuide Inc. You have to complete and settle each contract, including the resolution of any open items, and close each contract applicable to the project or a project phase. Which of the following processes will help you to accomplish the task?


A.

Report Performance


B.

Perform Quality Control


C.

Close Procurements


D.

Close Project or Phase