CSM-001 Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

The Sprint Backlog is owned by?


A.

The Scrum Master


B.

The Product Owner


C.

The Development Team


D.

The Scrum Master and Development Team