Exin EXIN EPI Certified Information Technology Manager CITM Question # 1 Topic 1 Discussion

Exin EXIN EPI Certified Information Technology Manager CITM Question # 1 Topic 1 Discussion

CITM Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

In project management, what is the objective of a 'lessons learned' report?


A.

To inform the project owner with the overall achievement of the project’s objectives


B.

To establish accountability for the mistakes being made in the project


C.

To identify all risks that occurred during the project


D.

Bringing forward positive and negative elements with the intent to benefit future projects


Get Premium CITM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.