You work as a project manager for TYU project. You are planning for risk mitigation. You need to quickly identify high-level risks that will need a more in-depth analysis. Which of the following activities will help you in this?
This method quickly identifies high-level risks using non-numerical assessments (e.g., likelihood and impact ratings) to prioritize risks requiring deeper analysis.
Risk Mitigation Planning:
Qualitative analysis provides a foundation for further investigation and mitigation efforts by highlighting critical areas.
Supporting Reference:
CCISO emphasizes qualitative analysis as an essential step in the initial stages of risk assessment for efficient risk prioritization.
=========================