What activities are conducted while developing an assessment plan?


A.

The C3PAO decides the Assessment Team members and notifies the Lead Assessor.


B.

The Lead Assessor and the OSC’s sponsor determine the assessment resources and schedule.


C.

The C3PAO’s project manager is responsible for handling potential conflicts of interest.


D.

The evidence collection approach can be finalized when the Lead Assessor conducts an onsite assessment.