A server administrator is testing a disaster recovery plan. The test involves creating a downtime scenario and taking the necessary steps. Which of the following testing methods is the administrator MOST likely performing?
The live failover testing method is the most likely one that the server administrator is performing when creating a downtime scenario and taking the necessary steps. A live failover test involves switching from the primary system to the secondary system (or backup site) in a real environment, without any simulation or preparation. A live failover test can evaluate the effectiveness and readiness of the disaster recovery plan, but it also carries a high risk of data loss, corruption, or disruption.Reference:https://www.ibm.com/cloud/learn/disaster-recovery-testing