PK0-005 Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?


A.

Rollback plan


B.

Release plan


C.

Deployment plan


D.

Contingency plan