CompTIA Project+ Certification (2026) PK0-005 Question # 7 Topic 1 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 7 Topic 1 Discussion

PK0-005 Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project’s level of compliance with the budget. Which of the following best describes what the project manager should do to assist the client?


A.

Grant the client access to the project repository.


B.

Create a chat to communicate in real time.


C.

Schedule a weekly status meeting.


D.

Send a weekly status report by email.