350-501 Exam Topic 17 Question 163 Discussion:
Question #: 163
Topic #: 17

A company is expanding its existing office space to a new floor of the building, and the networking team is installing a new set of switches. The new switches are running IGMPv2, and the engineers configured them for VLAN10 only. The rest of the existing network includes numerous Layer 2 switches in multiple other VLANs, all running IGMPv3. Which additional task must the team perform when deploying the new switches so that traffic is switched correctly through the entire network?


A.

Configure the new switches to use IGMPv3 on all VLANs on the network.


B.

Configure all switches on the network to support IGMPv2 and IGMPv3 on all VLANs on the network.


C.

Configure the new switches to use IGMPv3 on VLAN10 only.


D.

Configure all switches on the network to support IGMPv2 and IGMPv3 on VLAN10 only.