Cisco Troubleshooting Cisco Data Center Infrastructure (300-615 DCIT) 300-615 Question # 43 Topic 5 Discussion

Cisco Troubleshooting Cisco Data Center Infrastructure (300-615 DCIT) 300-615 Question # 43 Topic 5 Discussion

300-615 Exam Topic 5 Question 43 Discussion:
Question #: 43
Topic #: 5

A Cisco uCs C-Series Server powers off due to a power outage. The server should turn on when the power is restored with a fixed delay of 3 minutes. However, it remained powered off for more than 3 minutes after the engineer powered it back online. Which two actions resolve the issue (Choose two.)


A.

Configure the power-restore-policy.


B.

Configure the power restore last-state policy.


C.

Set the delay value to 180.


D.

Set the delay fixed value to 3.


E.

Configure power sync policy.