Cisco Troubleshooting Cisco Data Center Infrastructure (300-615 DCIT) 300-615 Question # 39 Topic 4 Discussion

Cisco Troubleshooting Cisco Data Center Infrastructure (300-615 DCIT) 300-615 Question # 39 Topic 4 Discussion

300-615 Exam Topic 4 Question 39 Discussion:
Question #: 39
Topic #: 4

Refer to the exhibit.

300-615 Question 39

A client configures an upgrade of its Cisco Nexus switches that are connected to the Cisco ACI controller, such that the switches are upgraded one at a time. After the upgrade is run, it is discovered that both Cisco Nexus switches were upgraded simultaneously. Which two actions ensure that the switches upgrade one at a time? (Choose two.)


A.

Configure the *Do not pause on failure and do not wait on cluster health" Run Mode


B.

Choose the 'Pause upon upgrade failure" Run Mode


C.

Select the "Graceful Maintenance" checkbox


D.

Place each leaf switch in a different upgrade group


E.

Check the Ignore Compatibility" checkbox


Get Premium 300-615 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.