An engineer Installs a B-Series server in a Cisco UCS chassis that contains a pair of UCS-IOM-2208XP I/O modules. The full bandwidth of the I/O module must be utilized. Which two elements should be used in this environment? (Choose two.)
A.
eight twinax cables from each I/O module to each fabric interconnect
B.
four twinax cables from each I/O module to each fabric Interconnect
2208 has 8 uplinks. VIC 1225 only works on C-Series UCS. M81KR has only 2x10G ports. VIC 1280 has 8x10G ports.