Question #: 6
Topic #: 1

Refer to the exhibit Due to power limitations at the customer data center, the engineering team must decommission one of the modular switches in the new design the customer must ensure that the OSPF process is fully protected on the remaining switch and minimize OSPF flapping in case of any module failure. Which solution fulfills the requirements for the new design?


A.

routing summarization


B.

graceful restart


C.

OSPF area separation


D.

LSA aging timer change