Cisco Designing Cisco Data Center Infrastructure (DCID) 300-610 Question # 1 Topic 1 Discussion

Cisco Designing Cisco Data Center Infrastructure (DCID) 300-610 Question # 1 Topic 1 Discussion

300-610 Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

Refer to the exhibit.

A Cisco engineer is configuring Cisco Nexus 7000 Series Switches To simplify initial configuration verification and vPC+/HSRP troubleshooting, the engineer configures the primary vPC+ peer device with the FHRP active router highest priority The primary FHRP device responds to ARP requests, even though the secondary vPC+ device also forwards the data traffic Which configuration enables the Layer 3 connectivity from each vPC+ peer device?


A.

Set a restore timer that delays the vPC+ restart


B.

Configure a VLAN network interface for the same VLAN from both devices


C.

Manually configure virtual MAC addresses for any FHRP protocol


D.

Ensure that the enhanced Layer 2 license has been installed.


Get Premium 300-610 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.