Question #: 25
Topic #: 3

300-415 Question 25

Refer to the exhibit vManage and vBond have an issue establishing a connection to vSmart Which two actions does the administrator take to fix the issue? (Choose two)


A.

Install the certificate received from the certificate server.


B.

Manually resync vManage and vBond


C.

Reconfigure the vSmart from CLI with the proper Hostname & System IP


D.

Delete and re-add vSmart Click Generate and validate CSR


E.

Request a certificate from the certificate server based on the CSR for the vSmart