L6M8 Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

Samir runs a small furniture manufacturing organisation and has recently decided to implement a Just-in-Time methodology. He has weighed up the pros and cons of this and has concluded it is the right thing for his business. Samir acknowledges that certain aspects of procurement will therefore need to change. Which of the following would Samir need to be aware of?


A.

he cannot change supplier


B.

he cannot make an error in the quantities ordered


C.

he must increase storage capacity for deliveries


D.

he must ensure fixed delivery dates with suppliers