CIPS Whole Life Asset Management L4M7 Question # 46 Topic 5 Discussion

CIPS Whole Life Asset Management L4M7 Question # 46 Topic 5 Discussion

L4M7 Exam Topic 5 Question 46 Discussion:
Question #: 46
Topic #: 5

What are the contents of master production schedule in MRP system?


A.

The investment required for production


B.

How many final products will be made and when to make them


C.

The total number of labour required to produce the final product


D.

What components and materials are and when to purchase them