CIPS Whole Life Asset Management L4M7 Question # 14 Topic 2 Discussion

CIPS Whole Life Asset Management L4M7 Question # 14 Topic 2 Discussion

L4M7 Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

What is the different between gross material requirements plan (gross MRP) and a net material requirements plan (net MRP)?


A.

The gross requirement doesn't take taxes into account, whereas the net requirement includes the tax considerations


B.

The gross MRP includes consideration of available inventory, whereas the net MRP does not


C.

The net MRP includes the amount of inventory on hand, whereas the gross MRP does not


D.

The gross MRP is mostly paper-based, but the net MRP must be computerised