CIPS Supplier Relationships L4M6 Question # 21 Topic 3 Discussion

CIPS Supplier Relationships L4M6 Question # 21 Topic 3 Discussion

L4M6 Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

A comprehensive approach to managing the termination of a contractual relationship would include ...


A.

Giving qualitative feedback only


B.

Attacking the personalities, not the problem


C.

Setting remedies and compensation for contractual breaches


D.

Setting aside the value of existing work done by both parties