A company plans a four-year project which will be financed by either an operating lease or a bank loan.
Lease details:
• Four year lease contract.
• Annual lease rentals of $45,000, paid in advance on the 1st day of the year.
Other information:
• The interest rate payable on the bank borrowing is 10%.
• The capital cost of the project is $200,000 which would have to be paid at the beginning of the first year.
• A salvage or residual value of $100,000 is estimated at the end of the project's life.
• Purchased assets attract straight line tax depreciation allowances.
• Corporate income tax is 20% and is payable at the end of the year following the year to which it relates.
A lease-or-buy appraisal is shown below:
Which THREE of the following items are errors within the appraisal?