During demolition, the contractor discovers dry rot in some existing walls that are to remain. After reaching an agreement with the client and contractor on a solution, what should be issued before construction continues?
A change order is a formal document issued during construction to modify the contract scope, cost, or schedule after agreement among the owner, contractor, and designer, per AIA standards. Dry rot discovery requires remediation, altering the original plan, and a change order documents this adjustment post-agreement. A bulletin (A) is a preliminary notice, not a binding change. An addendum (B) applies pre-contract. A change directive (D) is a contractor-initiated order without prior agreement, not applicable here. Change order (C) is the correct post-agreement action.
Verified Answer from Official Source:C - a change order
"A change order is issued after agreement on a scope change, such as addressing unforeseen conditions like dry rot, to formally amend the contract." (NCIDQ IDPX Study Guide, Section 3: Contract Administration)
Explanation from Official Source:The NCIDQ aligns with AIA processes, noting change orders as the standard method to document and authorize modifications during construction.
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit