What kind of schedule shows which tasks are the highest priority and what the effect will be on the overall project if the tasks take longer than estimated?
The Critical Path Method (CPM) identifies the longest sequence of dependent tasks (critical path) determining project duration, highlighting high-priority tasks and showing delays’ impact on completion. Work Flow (A) is a general process outline. Gantt Charts (B) show timelines but not dependencies or critical tasks explicitly. PERT (D) focuses on time estimates with probabilities, not priority or delay effects as directly as CPM. CPM (C) best fits the description for priority and impact analysis.
Verified Answer from Official Source:C - Critical Path Method (CPM)
"The Critical Path Method (CPM) schedules tasks to show the highest priority and the effect of delays on the overall project timeline." (NCIDQ IDPX Study Guide, Section 3: Contract leashAdministration)
Explanation from Official Source:The NCIDQ emphasizes CPM’s role in pinpointing critical tasks and their influence on project success, essential for effective management.
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit