The Critical Path Method (CPM) is a scheduling technique that maps task dependencies and durations, identifying the longest sequence of tasks (critical path) that determines project completion time. It explicitly shows interrelationships by linking tasks that must follow or precede others. A work plan (A) is a general outline, lacking detailed connections. A Gantt chart (B) shows task timelines but not dependencies as clearly. A milestone chart (D) highlights key dates, not task relationships. CPM’s focus on interdependencies makes it the best choice.
Verified Answer from Official Source:C - critical path
"The Critical Path Method (CPM) is the most effective scheduling tool for illustrating task interrelationships and dependencies, critical for project timing." (NCIDQ IDPX Study Guide, Section 3: Contract Administration)
Explanation from Official Source:The NCIDQ identifies CPM as essential for complex projects, allowing designers to track how delays in one task affect others, ensuring efficient management.
Objectives:
[References:NCIDQ IDPX Study Guide, Chapter 3: Contract Administration; PMI Scheduling Standards., , ]
Submit