CIDQ Interior Design Professional Exam IDPX Question # 2 Topic 1 Discussion

CIDQ Interior Design Professional Exam IDPX Question # 2 Topic 1 Discussion

IDPX Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

The interior designer presents budget options based on quality ranges and the client approves a budget on the low end. Throughout the design process, the client has added higher quality items and the project is now over budget. What could have been done to prevent this problem?


A.

Included a contingency line item in the budget


B.

Required the client to fill out preliminary budget sheets


C.

Reviewed the budget status more frequently with the client


D.

Redefined the specifications based on a square foot budget


Get Premium IDPX Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.