Blue Prism Accredited Developer Exam AD01 Question # 39 Topic 4 Discussion

Blue Prism Accredited Developer Exam AD01 Question # 39 Topic 4 Discussion

AD01 Exam Topic 4 Question 39 Discussion:
Question #: 39
Topic #: 4

A process is currently scheduled to run every day but needs to be temporarily stopped for 3 months According to best practice, how should this be done?


A.

Retire the Schedule for the required period. then Unretire it


B.

Clone the Schedule and set a new start date on the clone


C.

Set an End Date on the Schedule, then create a new Schedule to Start after 3 months


D.

Pause the Schedule for the required period


Get Premium AD01 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.