An ICT distribution designer is coordinating with local agencies for an upcoming campus improvement project which could affect the design. Which two of the following listed items will MINIMIZE design changes once the project begins? (Choose two.)


A.

Identification and agreement of conduit pathway routes


B.

Hand off of documentation to project manager


C.

Identification of maintenance holes, hand holes locations


D.

Approval of budget by chief financial officer (CFO)


E.

Approval of permit by AHJ - local Fire Marshal