Earned value analysis compares planned value, earned value, and actual cost to evaluate schedule and cost performance. In this question, the planned value is $1,000,000, while the earned value is only $700,000. Since earned value is less than planned value, the project has completed less budgeted work than planned for the measurement point. That indicates a negative schedule variance, meaning the project is behind schedule. Whether the project is over or under budget cannot be determined because actual cost is not provided. A project is ahead of schedule only when earned value is greater than planned value. Because $700,000 is less than $1,000,000, the correct conclusion is that the project is behind schedule.
================
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit