Program review meetings are used to monitor the overall health and progress of a project or program. Regular review topics commonly include schedule status, cost performance, scope, risks, issues, milestones, resources, dependencies, and major constraints. Project dependencies are especially important because delays or failures in one dependent task, supplier, component, team, or external interface can affect the entire program. Change request approvals are usually handled by a change control board. Quality system updates are typically handled through quality management reviews or process improvement forums. Problem reports may be reviewed when they affect project status, but they are not the primary regular program-level item among the choices. Therefore, project dependencies are the best answer.
================