Under the 8-level commissioning framework, the construction phase is critical for ensuring that project execution aligns with approved designs, regulatory requirements, and quality standards. The primary focus should be on staying within the planned timeline, budget, and performance criteria.
Adherence to Project Plans & Standards:
Ensure construction follows approved specifications, drawings, and material standards.
Monitor contractor performance to prevent deviations.
Quality & Compliance Monitoring:
Conduct regular inspections and implement the Three-Phase Control System (Preparatory, Initial, Follow-up phases).
Verify that work aligns with NAVFAC and DOE commissioning guidelines.
Schedule & Budget Control:
Track construction progress against the baseline schedule.
Address delays and cost overruns by analyzing root causes and applying corrective actions.
Defect Prevention & Issue Resolution:
Ensure proactive problem-solving to prevent rework and delays.
Maintain commissioning logs and punch lists to document issues and corrective measures.
Option A (Construction Waste Monitoring):
While waste tracking is important, it is a subset of quality management, not the primary focus.
Option C (Number of Construction Milestones Achieved):
Option D (Aesthetic Quality and Visual Appeal):
Visual quality is important, but compliance with technical and safety standards takes priority.
8-Level Commissioning Framework emphasizes project performance tracking, adherence to quality metrics, and compliance assurance.
Three-Phase Control System ensures that all quality checkpoints are met throughout the construction phase.
Key Evaluation Criteria During the Construction Phase:Why Other Options Are Incorrect:CQM References & Standards Applied:By ensuring strict adherence to schedules, budgets, and pre-approved standards, construction teams can deliver high-quality projects with minimal risks and defects.