Question #: 45
Topic #: 5

What should be included in the design of a strategy for conducting site quality audits in a dynamic construction environment?


A.

Conduct audits randomly to catch teams unprepared and identify genuine issues.


B.

Focus audits on areas where previous problems were identified to verify that root causes have been resolved.


C.

Plan regular, systematic audits and include mechanisms for immediate feedback and corrective actions.


D.

Prioritize audits of subcontractor activities while providing general oversight of other project areas.