CCQM Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

Which of the following contracting methods is typically used when a project requires specific expertise?


A.

Lump-sum contract


B.

Subcontracting


C.

Single-source procurement


D.

Competitive bid