Question #: 4
Topic #: 1

What is the most effective way to evaluate areas for improvement identified by CoQ data analysis?


A.

Focus improvements on the highest cost and impact areas


B.

Prioritize improvements based on ease and speed of implementation


C.

Assess the root causes of high CoQ areas and determine if improvements align with strategic objectives


D.

Implement random sampling techniques to choose areas for improvement